The Israeli Ministry of Environmental Protection report dated October 26, 2026, released in early November, identifies PFAS exceedances in six samples from four boreholes on plot 3205 in northern Sde Dov. This is a localized finding, not evidence that the entire plot is heavily contaminated. Buyers considering Aviv–Melisron should check current environmental instructions: the report decides neither a construction suspension nor a treatment cost.
Six samples from four boreholes exceed direct soil-contact thresholds. Most samples remain below those thresholds, many below the laboratory’s quantification limit. The volume requiring treatment, its cost and financial responsibility are not established.
Aviv–Melisron plans 320 homes alongside offices and retail on a plot of about 6 dunams in northern Sde Dov. Findings for this plot must be kept separate from investigations of other sites in the district.
PFAS means per- and polyfluoroalkyl substances. PFOS, perfluorooctane sulfonate, is one compound in that family measured in the report. The acronyms alone do not establish a health conclusion about an apartment.
The investigation used 12 boreholes, including two extended to approximately 17 metres. Its measurements describe the samples taken at the investigated points. They do not establish a uniform concentration across the whole plot or at every depth.
| Measure | Reported finding |
|---|---|
| Boreholes | 12 |
| Samples above thresholds | 6 from 4 boreholes |
| Documented PFOS sample | 19 333,6 ng/kg |
| Cited direct-contact threshold | 6 321 ng/kg |
| Concentration / threshold | Approximately 3.1 times |
The documented PFOS reading of 19 333,6 ng/kg is approximately 3.1 times the 6 321 ng/kg threshold. It is a sample-specific example, not a plot-wide average or a value applicable to every sample. Most samples remain below the thresholds, with many below the laboratory’s quantification limit.
A confirmed exceedance calls for focused document checks. Request the complete report, recent correspondence with the Ministry and any applicable soil-management requirements. The information should relate to the actual plot and development, not just to Sde Dov generally.
Possible effects on work sequencing or contractual obligations cannot be assessed without current instructions and documents. A laboratory concentration does not allow a buyer to calculate a delay or establish a treatment bill.
The investigation supplies laboratory findings; it is not itself an order that remediation has already been imposed. Any management measures will depend on the Ministry of Environmental Protection’s review and instructions. An investigation, an administrative direction and a construction schedule are separate matters.
This article distinguishes laboratory findings, administrative decisions and possible consequences. The detailed report figures were supplied for this update; automated access to the official PDF was unavailable during preparation. The original document is linked below for consultation. This analysis is not personalized legal, medical or financial advice.
No. Exceedances were identified in six samples from four of the twelve boreholes; most samples remained below the thresholds.
One sample contained 19 333,6 ng/kg of PFOS, approximately 3.1 times the direct-contact threshold of 6 321 ng/kg.
The report contains no decision suspending construction or the permit.
No. The report has not established a total volume, final cost or financially responsible party.
The plot’s environmental status, requirements imposed by the Ministry, contractual provisions for delays and costs, and the developer’s updated documents.